Activity Steps
Activity Steps is one of primavera feature which not used by a lot of primavera users, you can use it as a very important and useful feature.
It is simply subdivide the activity to steps which can help you to see the progress of this activity by each stop weight and every step progress.
Also it can be used to assign a lot of steps within the same activity instead of create a lot of activities.
Example:
Activity: Reinforced Concrete Work for Slab
Steps: 1- Slab Shuttering
2- Steel Fixing
3- Pouring
4- Curing
5- Slab De-shuttering
Where you can find Steps?
Activities > Steps
“As Shown in the photo below ”
How to add steps to any activity?
- Select your activity
- Form Steps tab
- Click add
- You have to fill step information
- Step Name
- Step % Complete “It is percentage refers to step competence percentage ”
-
Step Weight ” It refers to the weight of this step reference to the activity ”
You can put this weight by 2 ways
- Sep Weight : it is a number refers to it is weight
- Step Weight Percent : it is percentage refers to it is weight as a percent
-
Completed ” Check box refers to if this step completed or Not yet ”
As shown in the photo below “we divided Plain Concrete Activity into 4 steps ”
Step Shuttering Casting Curing De-Shuttering
Percentage 50 % 20% 20% 10%
How to make primavera Calculate the progress according to activity steps complete percentage?
Projects > Calculations > Activity Percent Complete based on activity Steps
You a can watch a tutorial video for Primavera
And more than 50 Primavera Tips and Tricks at our website with the following Link
We hope you enjoy our journey today
Hope to receive your feedback and recommendations
Thank You…